Project Milestones

Milestone

Start

End

  Project Kick-off

01 Nov 05

  Charter & Project Plan
  (Preparation – Approved)

02 Nov 06

30 Jan 06

  Reports version 1.0: Cert Process,
  IT PM Competency Framework,
  IT Professional Cert System Survey

13 Dec 05

22 Feb 06

  Planning the Launch of the IT Professional Certification
  Scheme

01 May 06

30 July 06

  Mutual Recognition Preliminary Study

01 May 06

30 Jun 06

  Consultation Process Cycle 1

25 Feb 06

30 Jun 06

  Interim Report

05 Jun 06

31 Jul 06

  Competency Framework for Systems Architect & QA
  Manager by EMB-Qualifications Framework

Mar 06

Aug 06

  Roster Feasibility Study

01 Jul 06

30 Oct 06

  Mutual Recognition Study & Liaison

01 Jul 06

09 Feb 07

  Consultation Process Cycle 2

01 Oct 06

31 Jan 07

  Conduct Launch of the IT Professional Certification
  Scheme (Preparation – Cert issuance)

Oct 06

Feb 07

  Peer Review

23 Feb 07

24 Mar 07

  Launch Review Report & Roster Feasibility
  Study Report

04 Dec 06

31 Mar 07

  Certification Process Report & Competency Models

03 Jan 07

10 Apr 07

  Mutual Recognition Report

12 Feb 07

20 Apr 07

  Final Report Issued

30 Apr 07

  Press Conference

03 May 07

10 May 07

  Project Closure

31 July 07